Press Release: 11/18/2026

Town Manager Releases Recommended Capital Improvement Program for FY2028-FY2032



 



Andover Town Manager Andrew Flanagan presented his Recommended FY2028-FY2032 Capital Improvement Program, which would invest $56,992,613 in maintaining and upgrading the Town's infrastructure, public spaces, and municipal and educational services.



The recommendations, which align with the Town's financial policies and long-term planning, will be funded through multiple sources, including General Fund revenue, Free Cash, and the Water and Sewer Enterprise Funds.



Over the five years of this CIP, the recommended CIP targets aging critical infrastructure, would invest in community priorities, and would improve existing conditions across diverse aspects of Town and school functions.



The FY2028 CIP recommendations seeks to balance the needs of the Town's core infrastructure—water and sewer, roadways and sidewalks, and modern equipment—with the things that make Andover what it is—community spaces, natural resources, and places to connect with one another.



To that end, the Town continues its Water Main Replacement Program by recommending $12 million for water main replacement. In the FY2027 CIP, the Town identified a goal of replacing four miles of water main per year. This $12 million appropriation supports the Town reaching that target in FY2028, as does the five-year water rate plan approved by the Select Board in May 2025. 



Additionally, the CIP recommends $6.5 million for the Water Treatment Plant, and $3.5 million for the Water Meter Replacement Program. Another $5 million is recommended for rehabilitating the Shawsheen Village Pumping Station.



The FY2028 CIP includes a recommendation for $5 million toward the Sidewalk Master Plan, with the goal of fully implementing it by FY2029. Doing so brings the Town's two-year investment in constructing and reconstruction of pedestrian infrastructure to a total of $10 million. The CIP also includes a recommendation for another $250,000 for minor sidewalk repairs.



Likewise, the FY2028 CIP makes recommendations that the Town invest $2.5 million to replace the Pomps Pond Bathhouse. The CIP recommends another $2.5 million to replace the synthetic playing surface at Lovely Field and upgrade the track—both of which have been used beyond their expected useful lives.



In addition to addressing facilities themselves, the CIP recommends investing in technology and materials Town and School employees utilize. The FY2028 recommendations include a request for $225,000 to replace four police cruisers, $180,000 to update student tablets and computers in Andover Public Schools, and $265,000 to replace some of the Town's vehicles used in different departments. 



Of the $56,992,613 investment recommended in the FY2028 CIP, $25.515 million is set to come from the Water Enterprise Fund and $6.25 million from the Sewer Enterprise Fund, which will be spent on water and sewer upgrades. 



General Fund Borrowing makes up $13.82 million of the recommended spending, focused on major improvement projects, like implementing the Sidewalk Master Plan and upgrading Town and School security. 



The $5.37 million coming from Free Cash is recommended to be spent on one-time improvements, such as minor sidewalk repairs and storm drainage. General Fund Revenues make up $3,567,240 of the recommendation to be used across town facilities, school maintenance, and other projects around Andover.



Finally, the CIP recommends the use of $2,469,873 for major annual roadway maintenance, supported by transportation funding from the state through Chapter 90 and the Fair Share Amendment.